In blowdown with a quick opening and slow opening valve on the bottom blowdown line, which valve is opened first and closed last?

Study for the Washington DC 1st Class Boiler Test. Prepare with comprehensive questions, each with explanations and insights. Equip yourself thoroughly for success!

Multiple Choice

In blowdown with a quick opening and slow opening valve on the bottom blowdown line, which valve is opened first and closed last?

Two valves in the bottom blowdown line are used in two stages: a quick-opening valve for a fast purge and a slow-opening valve for a controlled, gradual discharge. The quick-opening valve is opened first to rapidly drop pressure and flush out sediment and sludge from the boiler. After the initial purge begins, the slow-opening valve is opened to maintain a steady blowdown at a safer, controlled rate, which helps prevent water hammer and thermal shock. When shutting down, you close the slow-opening valve first to stop the controlled discharge, and then close the quick-opening valve last to ensure the line is fully shut off. This sequence means the valve opened first is also the one closed last.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy